A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

Determine the total mass of I2 in 25 grams of this typical tincture of iodine.
What is the smallest of 3 consecutive positive integers if the product of the smaller two integers is 5 less than 5 times the largest integer?
Which sentence is correct? My father wanted to know who’s dirty shoes were left on the new living room carpet. My father wanted to know whose dirty shoes were l
24 over 4 as a mixed number
A carbon-carbon triple bond is found in a molecule of (1) butane (3) butene (2) butanone (4) butyne
Round off 1,133,682,501 to the nearest thousand.
list five examples of "poe in your life"
Mental health professionals such as psychiatrists, psychologists, and social workers can help people cope with depression. What do psychiatrists do?
Find all powers of four in the range four through 1000
Which of the following was NOT a reason for population growth in the Sun Belt? Choose one answer. a. New industrial opportunities b. Strong labor unions c.