Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

If it is 2 degrees outside and the temperature will drop 15 degrees tonight , how cold will it get?
200 c how many quarters
Which substance is a molecule? A. water B. sodium C. salt water D. sand and salt
Which of the following is not a means of water erosion? A. Natural springs B. Rivers C. Streams D. Ocean waves
Which of the following is NOT a clear example of the application of the principle of specificity? a. lifting weights to build muscle strength b. running to bec
Why would someone want to file a lawsuit in a felony?
A rectangular, above ground swimming pool is 18 feet long, 9 feet wide, and 54 inches deep. One cubic foot of water weighs about 62.4 pounds. What is the total
who is the president now
Major events of young adulthood can include all of the following EXCEPT: a. starting a family b. selecting a job or career path c. entering into a committed rel
Which of the following is considered to be the most significant cause of erosion? a. water b. ice c. wind d. glaciers