Jin schedules 496 hours for a project. He plans to work 8 hours each day. How many days will it take to complete the project?​

Respuesta :

penguinlife90 penguinlife90
  • 01-12-2021

Answer:

62 days

Step-by-step explanation:

496/8 = 62

Answer Link
clickykeyboardasmr
clickykeyboardasmr clickykeyboardasmr
  • 01-12-2021

496/8=62

Hope this helps!

Answer Link

Otras preguntas

Which 4 countries did napoleon face during the battle of leipzig?
The allele for a widow’s peak has complete dominance over the allele for a straight hairline (w). What is the probability of two parents heterozygous for a wido
Suppose two pony express riders rode a total of 165 miles. If they replaced each horse every 11 miles how many horses would they have used
Start at 5. Create a pattern that multiplies each number by 3 and subtracts 2. Stop when you have 5 numbers.
1 - ¿qué hacen? write complete sentences using the cues provided. ellos / poder / ganar el partido ellos pueden ganar el partido.
I don’t understand this at all! Please help me!
If no file specification of a web page is specified in the web address, a default web page is displayed a. True b. False
What is measuring the age of fossils in years called
Which number can each term of the equation be multiplied by to eliminate the decimals before solving? –m + 0.02 + 2.1m = –1.45 – 4.81m
1.56 x 10 to the 4th power in Standard notation