a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

le apply for jobs online. sentence b. fragment a. 10. Difficulty with writing. a. sentence b. fragment 11. A complete sentence must have
What is Thermal Energy?
The healing of a cut finger. Is it a physical or chemical change? Explain.
According to the article, how do scientists think the Internet is changing the way people's brains work? A people spend more time online, some communication-rel
If your vehicle get stuck during a blizzard you should walk to the nearest house to get help. True or false
A triangle with vertices at A(0,0), B(0,4), and C(6,0) is dilated to yield a triangle with vertices at A(0,0), B(0,10) and C(15,0). The origin is the center of
what is considered an input and output peripheral?
why was it important to have an independent judiciary included in the constitution​
3.7+27 multipled by 5/7
The map shows the Roman Empire. A map titled Boundaries of the Roman Empire. A key shows areas of the Roman Empire during 2 time periods. Roman Empire in 201 B